20 November 2026
Blue Line Test Trains Run Through KR Puram as Namma Metro Crosses 100 km
BMRCL ran its first Blue Line test trains in November 2026. On 7 November a train ran between Byappanahalli Depot and Benniganahalli; on 10 November a test train travelled from the depot through KR Puram to Doddanekkundi, according to reports by The Hans India and IANS.
"Metro Blue Line train starts trial movement. During the last week, the train moved from the Bayyappanahalli test track to KR Pura and on to Doddanekkundi station. The trials will continue for some time."
— Minister Krishna Byre Gowda, quoted by IANS, 11 November 2026The Line and Its Timeline
The Blue Line has two parts: 19.75 km between Central Silk Board and KR Puram, and 38.44 km from KR Puram to Kempegowda International Airport via Hebbal. It is planned to connect with the Purple, Yellow and Pink lines.
Reported targets (these have slipped before)
- Central Silk Board–KR Puram: mid-2027.
- Hebbal–Airport: September 2027.
- Entire Blue Line: March 2028, moved from December 2027 in August 2026 (Deccan Herald).
- No passenger service is running on the Blue Line yet.
Separately, Namma Metro's operational network crossed 100 km on 13 November 2026, reaching 103.6 km when a 7.5 km elevated stretch of the Pink Line was inaugurated, PTI reported.
What It Means for East Bengaluru
KR Puram is about 14 km by road from Budigere Cross. When the Blue Line opens, KR Puram will become an interchange between the Purple Line and the airport line, which matters to anyone living along Old Madras Road. Until then, the practical connection for residents of this belt is the Purple Line terminal at Whitefield (Kadugodi), about 9 km from NVT Under The Open Sky.